Window Restoration
TOTAL RESORATION TIME FOR A SINGLE WINDOW WITH TWO 6 over 6 SASHES
30.75 hours
Remove both sashes, parting beads, and remove all paint from sills and casings. Clean up and prep time.
3.5 hours
Place sashes in steam box to soften the putty. Steam for 2 hours and remove putty and points with carving scraper.
2.5 hours
Heat gun and Bancho 665 carbide scaper to remove all paint from sashes.
8.25 hours
Sanded sashes and treated all surfaces with a 50:50 mix of balsam/linseed oil.
1 hour
Primed sashes. Primed sills. Oil based paint.
2.5 hours
Painted Interior side of sashes. Oil Based.
2 hours
Putty. Setting glass in putty and adding points. Tooling putty on mutins.
4.75 hours
Painting - coats oil based paint
1.75 hours
Cleaning the glass
.5 hours
Install Sashes. Install new ropes, new parting beads, and reinstall integrated weather stripping.
4 hours.
Tuesday, July 3, 2018
Saturday, May 5, 2018
Sunday, August 20, 2017
Side Patio
Prep work for a small patio next to the driveway.
Tamped with a jumping jack and then hand tamped after final grading.
Screeding the sand
Finally cutting in the pavers...way more work than I was expecting.