Tuesday, April 26, 2011

Beadboard painted

Hanson painted all the beadboard and medicine cabinet last week. We are waiting for all the baseboard and window casing, once we have that Hanson will paint it and the carpentry will install it next week.







Tile Completed

The tile is complete! Everything is grouted and completed. Next steps will be to have all the finish trim installed.








Friday, April 22, 2011

Subway Tile

Subway tile is all installed. Tomorrow morning the shower floor and walls will be grouted.






Monday, April 18, 2011

Hex Floor Grouted & Subway Tile

Floor was grouted today and shower walls were tiled. Waiting for the shelves for the shampoo niche, then the rest of the shower can be tiled and grouted.



Thursday, April 14, 2011

Hex Floor Tile

Floor tile was installed today, tomorrow it will be grouted and then shower pan will be tiled.





The shower pan got if's final coat of mud and the curb was also installed. Tomorrow the pan and walls will get waterproofed again and be ready for the subway tile.

Wednesday, April 13, 2011

Shampoo Niche and Waterproofing

The shower pan was waterproofed today and shampoo/soap niche was installed. Tomorrow the showerpan will get the final mud coat and the rest of the floor will be tiled. Hex floor tile and the 3x6 subway tile for the shower walls.

Tuesday, April 12, 2011

Floor Heat

Floor heat was installed last week. Tiler started today. Drain was installed, shower floor was mudded and sloped, and the main floor was leveled. Tomorrow the shower floor will be waterproofed and the floor tile will be set sometime after that.

Sunday, April 3, 2011

Paint

Sheetrockers finished up taping and mudding on Friday. Got the walls primed and painted and ready for the electrican to come back to install the floor heat. If we are lucky the tile might start to get installed at the end of the week.