The trim and beadboard was all installed today, starting to look like a finished bathroom. Picking up the vanity on saturday and then hopefully get plumbing and electrical fixtures installed.
Hanson painted all the beadboard and medicine cabinet last week. We are waiting for all the baseboard and window casing, once we have that Hanson will paint it and the carpentry will install it next week.
Floor was grouted today and shower walls were tiled. Waiting for the shelves for the shampoo niche, then the rest of the shower can be tiled and grouted.
Floor tile was installed today, tomorrow it will be grouted and then shower pan will be tiled.
The shower pan got if's final coat of mud and the curb was also installed. Tomorrow the pan and walls will get waterproofed again and be ready for the subway tile.
The shower pan was waterproofed today and shampoo/soap niche was installed. Tomorrow the showerpan will get the final mud coat and the rest of the floor will be tiled. Hex floor tile and the 3x6 subway tile for the shower walls.